Lucasville Road Bridge repair and upgrade

Profile photo of the Lucasville Road Bridge showing the western approach and elevation.

As part of the municipality’s 2024/25 Capital Plan the Lucasville Road bridge will undergo repair and upgrades starting April 2024 through January 2025. This work is necessary to ensure continued use of the bridge and modernization of some features in alignment with current construction standards. 

In addition to concrete repairs, the planned work includes:

  • installing new barriers and a wider sidewalk to improve pedestrian use;
  • removal of the expansion joints to reduce future maintenance; and,
  • repaving of Lucasville Road on the bridge and bridge approaches.

Project overview

Starting early April, contractors will begin pre-construction set-up which may result in minor traffic impacts. Construction is expected to begin mid-April 2024 through mid-January 2025. Although the bridge will not be closed during this period, starting late-May / early-June construction efforts will require reducing the bridge to one lane throughout construction. Crossing the bridge will be facilitated through signal lights operating 24 hours-a-day, seven-days-a-week throughout the construction period.

Current status

Concrete repairs began in mid-April 2024. This work will continue until early-June when it is expected construction efforts will require the bridge be reduced to single lane traffic. Crossing the bridge will be controlled by signal lights operating 24 hours-a-day, seven days-a-week during this period. Construction is expected to continue until mid-January 2025.

Public Service Announcements

Links to public service announcements are added here when published. Public service announcements are also published on halifax.ca/news and shared via @hfxgov on X.

 

Project contact

Kristin Thomas, Project Manager

Email: contactus@311.halifax.ca

Phone: 311