Location: Cumberland Drive between Cole Harbour Road and Colby Drive
Date: Tuesday, April 27 until the end of July
Time: Crews will be on site weekdays from 7 a.m. to 6 p.m.
Work details: This work includes a new concrete curb and gutter, upgrading the existing sidewalk to a multi-use pathway and paving of the roadway
Traffic impact: Lane drops will be in place while work is underway. Motorists should expect delays and are asked to use alternative routes whenever possible.
Construction during COVID-19: Construction crews will strive to maintain physical distancing measures, however, residents may see workers within two metres of each other while completing certain tasks which aligns with the exemptions outlined in the Provincial Health Order. If approaching construction crews, residents are asked to maintain at least two metres of physical distancing.
**********************
Emplacement : La promenade Cumberland entre le chemin Cole Harbour et la promenade Colby
Date : Du mardi 27 avril jusqu’à la fin de juillet
Heure : Les équipes seront sur place la semaine de 7 h à 18 h.
Détails du travail : Ce travail comprend une nouvelle bordure-caniveau, l’amélioration du trottoir existant en un sentier polyvalent et le pavage de la chaussée
Impact sur la circulation : Des fermetures de voies seront en place pendant que les travaux sont en cours. Les automobilistes doivent s’attendre à des ralentissements, et on leur demande d’emprunter d’autres voies dans la mesure du possible.
La construction pendant la COVID-19 : Les équipes de construction s’efforceront de maintenir des mesures d’éloignement physique, mais les résidents peuvent voir des travailleurs à moins de deux mètres l’un de l’autre tout en accomplissant certaines tâches qui correspondent aux exemptions prévues dans le Décret provincial sur la santé. À l’approche des équipes de construction, les résidents sont priés de conserver une distance physique d’au moins deux mètres.